Monthly Initiative Update:
Milestone Progress Snapshot [%]:
Provide a snapshot of progress for each milestone as of end of reporting period; May 31, 2024.
Targeted %* | Actual % | Comments | |
---|---|---|---|
Milestone I | 100% | 92 | Actively exploring the potential of a larger scope of work to help bring SafeDAO fully onchain, as bringing the Guardian role onchain has brought up questions for the SafeDAO team regarding the ideal evolution of the overall SafeDAO structure |
Milestone II | 100% | 35 | See above |
Milestone III | 0% | 0 |
*Targeted completion % is derived from the proposal timeline, understanding that some milestones may have been blocked from progression for valid reasons. These blockers are reflected in our reporting sheets.
Month | Amount Due | Executed |
---|---|---|
June | $2,500 | $2,500 |
CES Comment:
Safe Sign-Off:
Approved - Amy (OBRA DAO Commission) July 1, 2024
Approved - Lorny (OBRA DAO Commission) July 1, 2024