Monthly Initiative Update:
Milestone Progress Snapshot [%]:
Provide a snapshot of progress for each milestone as of end of reporting period; June 30, 2024.
Targeted %* | Actual % | Comments | |
---|---|---|---|
Milestone I | 100% | 100% | |
Milestone II | 100% | 60% | It’s been challenging to organize structured Webinars - we’re now switching our approach where we have a Themed day, and we invite many different projects from the Safe Ecosystem Database and will work with the first 1 - 2 partners who commit to the specific date and time. |
Milestone III | 80-90% | 80% | We’re wrapping up the second batch of articles which should be published before ETHCC and functions as input for the second iteration of the Safe Strater kit. |
Milestone IV | 80-90% | 60% | Six users have been adopted throughout the kit. We’re also working on an updated version of the Starter Kit, incorporating the new content pieces, and will give it a big push once it's completed. Expect to surpass our goal by the end of July. |
*Targeted completion % is derived from the proposal timeline.
Month | Amount Due | Executed |
---|---|---|
June | $6,250 USD | $6,250 USD |