Monthly Initiative Update:

Milestones Achieved:

Milestone Progress Snapshot [%]:

Provide a snapshot of progress for each milestone as of end of reporting period; May 31, 2024.

Targeted %* Actual % Comments
Milestone I 100% 100%
Milestone II 85% 75% - Working towards the System Improvement Report, which will constitute Milestone II’s main deliverable.
Milestone III ~50% 45%
Month Amount Due ($USD) Executed
June $12,500 $0

CES Comment:

[Recusing ourselves of comment]

Safe Sign-Off:

Approved - Amy (OBRA DAO Commission) July 1, 2024

Approved - Lorny (OBRA DAO Commission July 1, 2024