-Backend design still being discussed. Supposed to be finalized this week. - Kevin T doing awesome work starting front end, - Kelly and Yu exported design to Zeplin- need to confirm all there. - still need Google Tags, - will be tricky to get all done by Sept 21 but if we can get a backend to work then possible. > dependent on email notifications
- Kevin demoed the direct message in the dev environment.
- Mobile View Question Discussion: Continue to have the model for sending the initial message > Confirm Screen > View Message > Taking user to direct message
- The frontEnd is ready and ready to work on BackEnd. (Backend meeting with Josh, Luis, and Nicholas)
- Emily is working on pivoting to make sure direct messages can be separated by the Post.
- Emily/Tejas is working with backend engineering development to understand the level of effort.
- Emily is trying to see if a very interim messaging feature can be released before the launch date, but long term solution is still yet to develop.
- Emily has completed writing user stories for the backend.
- Backend, Architecture, and Data Modeling are still in Progress.
- Direct Messaging > Core Functionality and Direct Messaging > Notifications can be two separate tracks.
- Resources are all good now. PMs are discussing with Engineers to make a solid decision on the development.
- Zayd did a demo on Thursday with socket.io
- Emily to share the meeting notes with channel
- Meeting with Kelly, will be including non mvp features
- Blocking users, content moderation, active status, editing and deleting messages to be part of MVP.
- The messaging feature is under testing by QA and the FE needs help. Arshpreet will be helping with FE.
10/31/2020
- Mobile frontend implementation ready.
- QA in progress for build branch
- Merge on Stage by Nov 15